Nuclear Reactors: Delayed & Over Budget
Views: 778
Mar 31 2016 01:15 PM | eds in Non-Renewable
2 Georgia Power nuclear reactors,
. . . (at Plant Vogtle in Burke County, along the Savannah River),
. . . 6 years into construction, the project is
. . . 39 months behind schedule,
. . . with more delays, and cost overruns likely.
The 1st reactor, was to be operational on April 1, 2016,
. . . now won't be operational until 2020 or 2021.
In 2015, the Georgia Public Service Commission staff,
. . . developed an estimate of the impact of the 39-month delay,
. . . on residential ratepayers' bills.
A residential customer with average monthly usage of approximately
. . . 1,000 kWh will pay approximately
. . . $319 during the delay period of April 2016 through June 2020,
. . . for additional financing cost and replacement fuel cost, an average of
. . . $6.26 per month.
3-31-2016 Source: Nuclear Reactors: Delayed & Over Budget
. . . (at Plant Vogtle in Burke County, along the Savannah River),
. . . 6 years into construction, the project is
. . . 39 months behind schedule,
. . . with more delays, and cost overruns likely.
The 1st reactor, was to be operational on April 1, 2016,
. . . now won't be operational until 2020 or 2021.
In 2015, the Georgia Public Service Commission staff,
. . . developed an estimate of the impact of the 39-month delay,
. . . on residential ratepayers' bills.
A residential customer with average monthly usage of approximately
. . . 1,000 kWh will pay approximately
. . . $319 during the delay period of April 2016 through June 2020,
. . . for additional financing cost and replacement fuel cost, an average of
. . . $6.26 per month.
3-31-2016 Source: Nuclear Reactors: Delayed & Over Budget